Network charging – what’s been going on and why should I care?

Across Great Britain there are ~810,000km of wires and underground cables that make up our electricity network. Split between the higher voltage, transmission system and the lower voltage distribution system, these lines and cables are responsible for transporting electrons up and down the country to provide consumers with the necessary electricity they need.

However, accessing, and subsequently using the network costs money. Use of the transmission system will incur transmission network use of system charges (TNUoS), while using the distribution system will make you liable for distribution use of system charges (DUoS). In recent years, Ofgem and wider industry have been reviewing how users can access the network and consequently how they should pay for using it. With lots of changes going on, and over a long period of time it can be tricky to keep a handle on all these reforms, but with generators, suppliers, consumers and storage operators all impacted in some way it’s important to be in the know and keep up with the latest developments.

Where have we been?

As an industry, we are edging ever closer to the end of two separate network charging significant code reviews (SCRs). The Targeted Charging Review (TCR) is almost complete and come April 2023 – aside from any further housekeeping amendments – all intended reforms should be implemented. This includes changes to the residual charges for DUoS and TNUoS, as well as changes to the balancing services use of system (BSUoS) charge so that it is based on gross demand, rather than net, and only paid by final demand users. The BSUoS reforms will remove distortions both within GB, between the transmission network and the distribution network, and between GB and the EU given EU generators are not liable for balancing charges.

The second SCR nearing completion is the Access SCR. While it was originally supposed to include wide-ranging DUoS reforms, as well as assessing the possibility of TNUoS for small, distributed generators, the final direction just addressed changes to access rights and the connection boundary. We will come on to what happened to the further DUoS and TNUoS developments, but the access rights and connection boundary reforms are currently at code modification workgroups. The outcomes of the Access SCR are intended to support earlier connection to the network, and reduce the costs paid by connectees when connecting to, and reinforcing the network. Ofgem considers this should support the deployment of low carbon technologies as well as facilitating the rollout of electric vehicle infrastructure.

Where are we going?

Nearing the end of two network-related SCRs is no reason for laurels to be rested upon. Ofgem is already beginning two new workstreams to further consider network charging reform. A formal DUoS SCR is in the making, which will cover the wide-ranging review of DUoS that previously sat within the Access SCR but was subsequently broken out. Further industry participation will begin in the coming months. The second workstream is the launch of TNUoS Task Forces. Applications are currently open for the first Task Force which will consist of 16 members including Ofgem, the ESO, as well as supplier, generator and storage operator representatives. While fundamental reform of the TNUoS model and methodology is off the table for now, the Task Force may well still result in tweaking to the methodology along with a set of CUSC modifications to address any identified defects.

We are still waiting for clarity on much of the work to be completed through DUoS SCR and TNUoS Task Forces, and we will be providing regular updates on all developments falling out of these workstreams through our regulatory service as and when we get them. We will be issuing alerts on the key policy decisions; our modifications and consultations registers, and weekly reports will provide insight on minded-to positions and code modifications; and we will be discussing all the updates at our supplier, generator and flexibility forums.

There is a clear understanding that network charging reform is going to be completely necessary if net zero targets are to be met. Ensuring the right incentives are provided to the right users both when connecting to and using the network will be essential. While impacts to consumers can be minimised, there is also a clear need for investment in the network meaning that the network element of the consumer bill is unlikely to drop any time soon. However, the ways in which consumers interact with and access the network is likely to change in the future and there may be cost savings and revenue opportunities arising from network innovation.

For more information on our regulatory service or to find out more about how we can support your business through the network charging landscape please get in contact with Tom Faulkner on 01603 542123 or email t.faulkner@cornwall-insight.com.

Related thinking

Home supply and services

Highlights from our Energy Supplier Compliance webinar

As part of our Energy supplier compliance portal service, we run a webinar every 6 months which looks at key updates.    Our latest webinar looked back at the decisions made under Ofgem’s financial resilience plan. This included strengthening milestone assessments and introducing additional reporting requirements. It also decided on the short-term interventions...

Energy Market Design

REMA: electricity market design choices

Electricity markets will serve as the foundation for the future GB energy system.  This article examines some of the market design decisions that will be considered by the Review of Electricity Market Arrangements (REMA). Market design goals At its most simple, a well-functioning market will attract enough potential “buyers” and...

Low carbon generation

Energy System Reform: Ofgem shares plans for Britain’s energy system

Against the backdrop of record high and volatile energy prices, Ofgem set out on 8 July its view on key aspects of the GB energy system where it considers significant reform is required to deliver a resilient, low cost, low carbon energy sector. Recent developments in the energy market, such...

Regulation and policy

The changing compliance landscape

In recent months, Ofgem has been increasing its engagement with suppliers to ensure compliance with their supply licences and to deliver more resilient business models. This has been evidenced through a number of actions, such as stress testing suppliers and introducing additional reporting requirements, under the scope of the regulator’s...

Energy storage and flexibility

National Grid ESO’s ‘early view’ winter report 2022/23

We have published an alert on National Grid Electricity System Operator's Winter 2022/23 early view report.  The ESO considers that it is important for industry to be provided with a rough understanding of the situation to come, through the early view report. It is operating under the assumption that the peak...

Energy storage and flexibility

Dialing up the unknowns on network charging

In a world of open governance code modifications, change is a constant. You only have to look at the number of code modifications ongoing at any one time – National Grid lists 36 modifications in development relating to transmission network charging alone – for evidence of that. But in recent...

Commercial and market outlook

Two thirds of energy industry professionals think the market needs to be drastically reformed

A survey conducted of over one hundred leading energy market professionals from across the investment and advisory community, by Cornwall Insight, from the attendees of its Financing Net Zero forum, has shown nearly two thirds (63%) of people working in the energy industry1 believe the UK market needs to be...

Home supply and services

Making the switch – how much will really change?

Last week on 1 July, Ofgem confirmed that the designated Go-Live date for the Centralised Switching Service (CSS) would be 00:01AM on 18 July 2022, as was previously anticipated. The most significant impact of this will be the requirement on suppliers to ensure switches are completed within five working days,...