This week National Grid Electricity System Operator (“the ESO”) released its latest forecast of Balancing Services Use of System (BSUoS) charges – levied on suppliers and large generators to recover costs incurred by the ESO in managing the system on a second by second basis. In this blog we look at the impact COVID-19 could have on BSUoS costs and a recent proposal to mitigate the impact.

The ESO has been forced to take unprecedented actions as a result of low demand on the system driven by the COVID-19 lockdown, including:

  • Launching a new commercial service (known as “Optional Downward Flexibility Management”) for demand turn-up/generation turn-down.
  • Clarifying its ability to instruct distribution network operators (DNOs) to disconnect generation connected to the DNO networks.
  • Reaching a deal with EDF to reduce output from the Sizewell B nuclear plant throughout the summer.

These additional services, along with increased use of existing services to (for example) reduce generation output through the Balancing Mechanism, are expected to materially increase BSUoS costs over the coming months. The ESO’s latest forecast for May to August 2020 totals £911mn compared to £439mn in the same period in 2019. Alongside the significant increase in absolute cost, demand in the same period is forecast to be down by around 13% between 2019 and 2020, further exacerbating the increase when converted to £/MWh. The average rate across May to August 2020 is now forecast to hit £7.45/MWh, compared to £3.13/MWh in 2019.

The ESO has been keen to point out that the costs would have been even higher without additional services. Its estimates show the costs across the same four-month period could have been as high as £1,124mn without new services. But that will provide little solace to parties facing materially higher BSUoS bills.

As a result of the unforeseen increase, SSE Generation has proposed a modification to the Connection and Use of System Code (CUSC) seeking to soften the impact. That modification (CMP345) would see £500mn of BSUoS go unrecovered between May and August and instead recovered across the entirety of April 2021 to March 2022.

The chart shows:

  • Historic BSUoS cost for the past year.
  • The ESO’s central forecast for actual BSUoS costs going forward and the associated BSUoS rate.
  • The ESO’s estimate of the BSUoS costs which would be incurred without its new services and the associated BSUoS rate.
  • The BSUoS cost to be recovered should CMP345 be approved with costs deferred into 2021-22 and the associated BSUoS rate.
  • We are running our Electricity settlements: from the meter to the bank course, online from 2-4 June where we will discuss MHHS in more depth. Find out more here.

Related thinking

Energy Market Design

REMA: electricity market design choices

Electricity markets will serve as the foundation for the future GB energy system.  This article examines some of the market design decisions that will be considered by the Review of Electricity Market Arrangements (REMA). Market design goals At its most simple, a well-functioning market will attract enough potential “buyers” and...

Energy storage and flexibility

National Grid ESO’s ‘early view’ winter report 2022/23

We have published an alert on National Grid Electricity System Operator's Winter 2022/23 early view report.  The ESO considers that it is important for industry to be provided with a rough understanding of the situation to come, through the early view report. It is operating under the assumption that the peak...

Energy storage and flexibility

Network charging – what’s been going on and why should I care?

Across Great Britain there are ~810,000km of wires and underground cables that make up our electricity network. Split between the higher voltage, transmission system and the lower voltage distribution system, these lines and cables are responsible for transporting electrons up and down the country to provide consumers with the necessary...

Business supply and services

Re-balancing the balancing costs –BSUoS charges to be levied solely on suppliers from April 2023

Balancing the electricity system costs money. National Grid in its role as Electricity System Operator (ESO) takes actions in every half hour to achieve the remarkable feat of keeping supply and demand finely balanced on our national electricity system – maintaining a system which runs between 49.8 and 50.2Hz with...

Energy storage and flexibility

Dynamic Regulation launches

National Grid ESO (NGESO) launched the Dynamic Regulation (DR) service on 8 April, with the first auction held at 14:30 on the EPEX auction platform. DR is the second new product that the ESO has introduced to manage frequency on the system, as the system operator introduces a suite of...

Low carbon generation

What to look out for in Third Party Charges in 2022-23

In recent months, the GB energy market has been exposed to extreme volatility as wholesale prices have grown rapidly, leading to a significant number of supplier exits and questions over consumer affordability of energy bills. This has resulted in notable movement across a number of non-commodity costs (also known as...

Power and gas networks

New Fault Ride Through compliance arrangements introduced for transmission-connected generators

Ofgem approved Workgroup Alternative Grid Code Modification 1 (WAGCM1) of GC0151 Grid Code Compliance with Fault Ride Through (FRT) Requirements on 5 November. In short, this decision introduces a new, legal process, into the Grid Code – the legal text that governs those connecting to the electricity transmission system -...

Power and gas networks

Location, location: The increasing complexity of embedded benefits

There is growing recognition of the need to reform our current network arrangements to support a more dynamic and flexible electricity system as we undergo the transition to net zero. Among the network elements currently going through a period of review are Distribution Use of System (DUoS) charges, which recover...