As we await the full results of the latest T-4 Capacity Market, which has delivered the lowest clearing price to date for this type of auction, we have been reflecting on the possible business cases for large-scale battery storage. I was speaking on this very topic at the Energy Storage and Connected Systems event in London earlier this week and would like to share our thinking in this area with a wider audience.

We have worked with numerous battery storage developers, investors and traders in the past three years, and while every site has its own design and complexities, the business models can be largely put into three categories: standalone (grid connected); co-located (either with renewables or fuelled generators); and behind the meter for a major consumer.

The standalone option is where we have seen the most activity from a new capacity point of view. This currently tends to be focused on providing services to support the grid through frequency – there is 201MW providing enhanced frequency response (EFR) through the one and only tender of this service in 2016, and a further ~100MW of batteries with firm frequency response (FFR) contracts. The former are four-year contracts which many investors may have considered to be the panacea from a certainty of revenue perspective, sadly for them these contracts are no longer being tendered by National Grid. FFR is available for up to 30 months and therefore offers some price certainty, but this is an increasingly competitive market with an observed fall in prices.

Both these revenue streams can be “stacked” with others to improve the economics and widen the services offered by the batteries. The Capacity Market is one and this potentially offers a 15-year agreement to provide some stability/ certainty to overall revenue streams. Sadly, from an investor point of view, a new one-hour battery in the T-4 will now be de-rated to 36% of its capacity, rather than the previous 96%. This recent regulatory change was on the back of evidence from National Grid that suggested a Capacity Market stress event may last 1.8 hours.  

The other stacked revenue possibility for this business model is embedded benefits. Depending on the connection and frequency contract timings, there may be an opportunity to capture some value from embedded benefits, which I’m sure you’re all aware, have recently been reduced through the Triad review.

Given the increasing competition in the FFR space and sharpening market price signals (both wholesale and imbalance), other strategies are evolving for standalone battery assets. Perhaps for those looking to get debt into their projects, they may consider an arbitrage option as a downside case. This is where the value arises from a combination of wholesale market trading (day-ahead and within-day), the Balancing Mechanism (either directly or indirectly access), potentially another National Grid balancing service (e.g. Fast Reserve) and of course the Capacity Market. Given the introduction of PAR1 imbalance pricing later this year and the increasing penetration of renewables on the system leading to spikier short-term wholesale pricing, this business case may start to look more appetising to developers (but possibly not investors given the lack of price certainty). There are many further complexities to this option, but on a positive note, falling battery costs will make this option more viable generally, and the wholesale market and Balancing Mechanism are significantly deeper markets than frequency response.

Moving onto co-location. This is a complex option but potentially offers greater investor protection as the business model can be more diverse. We have seen some developments of this type in Britain, for instance Anesco’s co-location of solar and batteries. On the one hand, a battery situated alongside solar/ wind may look to shift the load and release the power at more beneficial times of day to maximise the value of the output into the wholesale market. Alternatively, the battery may provide services to National Grid, akin to the standalone option; or, indeed, it may do a combination of the two (in separate windows). In addition, its likely this type of asset will look to achieve further value through the Capacity Market and embedded benefits. This configuration benefits from some shared costs, both connection and O&M.

A major concern for this business model had been fears over losing RO/ FiT accreditation for solar/ wind co-location by making changes to the site. This had centred on addition of storage being deemed to a major change to the site and therefore requiring the solar/ wind project to go through subsidy accreditation again. For the RO, this would mean no more subsidy, as the scheme has now closed to new accreditations. Good news on this front though, as Ofgem has recently published a consultation on guidance for co-locating and maintaining accreditation. One further issue worth considering though is cash-flow under the RO as while Ofgem assesses the changes you make by co-locating storage, your Rocs are suspended, leaving a (hopefully) temporary hole in your revenues.

This is an exciting option, not just for renewables, but there remain some questions over whether it genuinely opens up opportunities for commercially-viable subsidy-free renewables.

Finally, the behind the meter strategy. This is starting to take off in Britain, with low 10s of megawatts being commissioned alongside industrial and commercial sites in the past year. This business case is centred on reducing the electricity costs for major consumers by in effect taking them off the grid (to a degree) over peak times, especially 4pm-7pm on winter weekdays. The costs being avoided include red rates of distribution use of system (DUoS), transmission network use of system (TNUoS i.e. triads) and the Capacity Market supplier charge. All of these costs have increased in recent years and are some are set to continue according to Cornwall Insight’s latest assessments in our Third Party Charges reports.

There is a compelling case for such applications, but they do not come without their drawbacks. The multiple parties (e.g. consumer, battery owner, aggregator) involved can result in contracting complexities and there are some regulatory risks to be aware of, including Ofgem’s Targeted Charging Review, which is focusing on how network use of system charges are levied on consumers and has hinted at looking at behind the meter/ private wire consumers as part of the review.

Cornwall Insight offers a wide range of support to those looking to develop, invest and run battery storage and generation assets. This includes forecasts of frequency response, Capacity Market clearing prices and Third Party Charges (i.e. non commodity costs). We also provide training courses on flexibility and trading and have supported a wide range of flexibility and renewables assets from a regulatory, policy and commercial angle. If you would like to hear more, please get in touch with our associate director, Ben Hall b.hall@cornwall-insight.com.

Related thinking

Energy Market Design

REMA: electricity market design choices

Electricity markets will serve as the foundation for the future GB energy system.  This article examines some of the market design decisions that will be considered by the Review of Electricity Market Arrangements (REMA). Market design goals At its most simple, a well-functioning market will attract enough potential “buyers” and...

Energy storage and flexibility

Dialing up the unknowns on network charging

In a world of open governance code modifications, change is a constant. You only have to look at the number of code modifications ongoing at any one time – National Grid lists 36 modifications in development relating to transmission network charging alone – for evidence of that. But in recent...

Commercial and market outlook

Capacity, reform, and unlawful strategies: 5 things that happened yesterday

Capacity, reform, and unlawful strategies: yesterday was a busy day for energy geekery. The developments encapsulate the shorter and longer term challenges and uncertainties present in the energy market presently: Read the full article here

Business supply and services

Re-balancing the balancing costs –BSUoS charges to be levied solely on suppliers from April 2023

Balancing the electricity system costs money. National Grid in its role as Electricity System Operator (ESO) takes actions in every half hour to achieve the remarkable feat of keeping supply and demand finely balanced on our national electricity system – maintaining a system which runs between 49.8 and 50.2Hz with...

Low carbon generation

Reform in haste, repent at leisure: squaring electricity market reform with investor confidence

The review of electricity market arrangements (REMA) signalled by the energy security strategy could impact wholesale & balancing markets, & there could be a need to examine the capacity market rules & CFD contracts. It is too early to know what options will ultimately be adopted or when changes would...

Energy storage and flexibility

Dynamic Regulation launches

National Grid ESO (NGESO) launched the Dynamic Regulation (DR) service on 8 April, with the first auction held at 14:30 on the EPEX auction platform. DR is the second new product that the ESO has introduced to manage frequency on the system, as the system operator introduces a suite of...

Commercial and market outlook

Cornwall Insight responds to the publication of the energy strategy  

The Energy Security Strategy is a very political document that raises as many questions as it answers. There are clear favourites and as much can be read in to what is in the Strategy as what is not. 15 months on from the Powering Our Net Zero Future White Paper,...

Commercial and market outlook

Perspective | Is the design of the electricity market costing consumers money?

This article is from our Energy Spectrum publication which was published on 4 March 2022. It has become increasingly clear the existing market design is unfit for either a future net zero world or a period of fossil fuel price crisis, but what market design might be best for our...